SSEN (Scottish & Southern Electricity Networks) has launched a consultation for the future of the north of Scotland electricity transmission system.
‘A Network for Net Zero’ aims to support both the UK and Scottish Governments’ targets and meet the needs and expectations expressed by stakeholders through five clear, ambitious goals:
- Transport the renewable electricity that powers 10 million homes (circa 10 GW)
- 100% network reliability for homes and businesses
- Every connection delivered on time
- One third reduction in SSEN Transmission’s greenhouse gas emissions
- £100m in efficiency savings from innovation
Rob McDonald, Managing Director for SSEN Transmission said:
“Our network already supports over 6GW of clean power but continued investment in the electricity transmission system is key to unlocking the further potential the North of Scotland can play in meeting Governments’ targets for net zero greenhouse gas emissions.
“Our ‘Network for Net Zero’ proposal is a balanced package that makes a powerful case for the vital investment needed to deliver the clean energy transition, reflecting the ambition our stakeholders have told us they want to see, at an affordable cost to consumers, whilst also providing a fair return to investors.”
In the draft Plan, SSEN Transmission’s ‘Certain View’ sets out that a minimum investment of £2.2bn is required over the five-year period to maintain and grow the north of Scotland transmission network to meet the certain needs of current and future electricity generators and customers.
A significant proportion of this investment will take place in the north east, with a particular focus on accommodating the growth in offshore wind in the area.
It is anticipated additional investment will be required to deliver the transition to net zero, but this investment will only be released once there is certainty it is needed – protecting bill payers.
To deliver its plans, SSEN Transmission estimates its average cost to the GB consumer over the RIIO-T2 period will be around £7 a year.
The consultation closes on 31st of August. Click on the link for more information and to respond: A Network for Net Zero